IBM-AUSTRIA - PC-HW-Support 30 Aug 1999 |
Installing the Top Cover
Installing the Top Cover
Completing the Installation
To complete the installation, you must reinstall the side
and top covers, reconnect all the cables that you
disconnected in 'Preparing to Install Options', and, for
certain options, run the Configuration
utility program. Follow the instructions in this section.
For correct cooling and airflow, install the top cover
before turning on the server. Operating the server for
extended periods of time (over 30 minutes) with the
top cover removed might damage server components.
To install the server top cover:
- Before installing a cover, check that all cables,
adapters, and other components are installed and
seated correctly and that you have not left loose tools
or parts inside the server.
- Lower the cover -2- with the rear edge of the cover
about 25 mm (1 inch) back from the rear edge of the
server.
- Slide the cover forward.
- Tighten the two thumbscrews -1- on the back edge of
the cover.
- If you disconnected any cables from the back of the
server, reconnect the cables, then, plug the power
cords into properly grounded electrical outlets.
Note:
- If you are in the United Kingdom and have a
modem or fax machine attached to the
server, reconnect the telephone line after
you plug in the power cords.
- If necessary, see 'Input/Output Connectors and Expansion Slots'
for connector locations.
Back to
More INFORMATION / HELP is available at the IBM-HelpCenter
Please see the LEGAL - Trademark notice.
Feel free - send a for any BUG on this page found - Thank you.